Item Coversheet
Item #1.

Staff Report 136-21

TO:

Mayor and City Council




FROM:

Eric Holmes, City Manager




DATE:

9/27/2021








SUBJECT


Bid Award - Southside Interceptor CIPP Sewer Rehabilitation Phase 2
Key Points
  • The project will install approximately 2,800 total linear feet of 36-inch Cured-In-Place Pipe (CIPP).
  • The City received 4 bids for the project.
  • Staff proposes awarding a contract to the lowest, responsive bidder, Allied Plumbing & Pumps of Wenatchee, WA at the bid price of $976,348.10.

Strategic Plan Alignment

 

Goal 1, Objective 1.2: Ensure our infrastructure, including buildings and utilities, is safe, environmentally responsible and well maintained.


Present Situation

This project will rehabilitate approximately 2,800 linear feet of existing 36-inch interceptor sewer mains using the trenchless process of Cured-In-Place-Pipe (CIPP). The Southside Interceptor is part of the backbone of the sewer system that transports wastewater to the Westside Reclamation Facility. This project is the result of an interceptor condition assessment project completed in 2016 that provided a list of capital projects needed to maintain the system.

 

On August 31, 2021, the City received 4 bids for the subject project. The bids ranged between $976,000 and $1,562,000.00. The bids are as follows:

 

SUMMARY OF BIDS

BIDDER

AMOUNT

Allied Plumbing & Pumps, Wenatchee, WA

$976,348.10

Iron Horse, LLC, Farview, OR

$1,390,249.56

Michels Corporation, Salem, OR

$1,531,673.89

Insituform Technologies LLC, Chesterfield, MO

$1,561,384.44

Engineers’ Estimate

$1,440,000.00

 

An Apprenticeship Program Waiver Request was approved for this project. A copy of the waiver request is attached. From experience with past similar CIPP projects the City has confirmed that for rehabilitation projects that utilize CIPP trenchless technology, the labor hours and subsequent labor costs required to complete the project are very low compared to the higher cost of the materials needed. Using the projects that appear in the waiver request, the Central Van North project, which was built with traditional open-trench digging methods, had approximately 47% labor costs and 53% materials/other costs. The Southside Interceptor CIPP project had approximately 14% labor costs and 86% materials/other costs. 

 

Following the City’s current apprenticeship policy, this project meets both of the criteria for waiver of an apprenticeship requirement: the project is a high materials cost but low labor hours project, and the contractor will only be allowed 30 working days to complete the work.


Advantage(s)
  1. Completion of the project will follow the recommendations of the Interceptor Condition Assessment Study as well as asset management criticality models.
  2. Allows for the continuing provision of high quality reliable sewer service.

Disadvantage(s)
None
Budget Impact

None. Sufficient budget for these sanitary sewer improvements was appropriated in the 2021-2022 Sewer Construction Fund, Capital Improvement Program.  


Prior Council Review

Funding previously reviewed by Council in the context of the 2021-2022 Sewer Construction Fund Capital Budget.


Action Requested

Award a contract contract for the Southside Interceptor Phase 2 - CIPP project to the lowest responsive and responsible bidder, Allied Plumbing & Pumps of Wenatchee, WA at their bid price of $976,348.10, which includes Washington State sales tax.

 

Sheryl Hale, Senior Engineering Supervisor, 360-487-7151

 


ATTACHMENTS:
Description
Contract
Boundary map
Apprenticeship Waiver Request