Item Coversheet
Item #2.

Staff Report: 075-24

TO:

Mayor and City Council




FROM:

Eric Holmes, City Manager




DATE:

4/15/2024








SUBJECT


Bid Award - 2024 Joint Agency Slurry Seal Project
Key Points
  • The City maintains approximately 1,900 lane miles of streets in its system.
  • The City’s annual resurfacing and preservation contracts are the primary way that the streets get curb to curb work done on them.
  • The project includes approximately 29 lane miles of street preservation.
  • City maintenance crews do not have adequate staff, or equipment to do the type of work being done as part of this project.

Strategic Plan Alignment
Transportation and Mobility - a safe, future-ready and convenient transportation system.
Present Situation

The City of Vancouver and Clark County have solicited a joint bid for each agency’s 2024 Joint Agency Slurry Seal Project. Each agency will execute a separate contract for their part of the work. 

On March 26, 2024, the City received five bids for the 2024 Joint Agency Slurry Seal Project.  Two bidders were non-responsive. The bids ranged from $669,471.16 to $1,015,160.52. The low bidder was responsive.  The estimated 2024 City of Vancouver part of the work is $412,030.00.

 

SUMMARY OF BIDS

BIDDER

VANCOUVER’S BID

COMBINED BIDS

Blackline, Inc, Vancouver, WA

$412,030.00

$669,471.16

 

Doolittle Construction, LLC, Sacramento, CA

$518,135.80

$858,858.00

 

One Way Trigger, LLC, Sacramento, CA

$591,810.00

$1,015,160.52

 

Engineers’ Estimate

$440,000.00

$749,285.76

 

 The engineer’s estimate of $440,000.00, which covers the City’s portion of the cost, is below the $500,000.00 threshold requirement set for apprenticeship utilization goals. No apprenticeship utilization goals are required for this project.


Advantage(s)
  1. Will result in improved pavement on approximately 29 lane miles of streets in Vancouver, protecting the City’s investment in its street network.
  2. The City of Vancouver and Clark County are working cooperatively to make the best use of limited funds by reducing construction costs through economies of scales.
  3. Will reduce higher maintenance costs on City streets as well as extend the life of the pavement before more costly treatments are required.

Disadvantage(s)
  1. Neighborhood residents, businesses and local traffic will be inconvenienced during the construction period at the various locations; however, the construction duration at each location is short, with traffic able to drive over the new surface within a few hours at most, which will minimize the temporary inconvenience.
  2. Construction will generate noise in the area; however, the contractor will not be working in one spot the entire time with all work expected to be complete a few days at each location.

Budget Impact
The project is currently funded through the Pavement Management Program in the Street Fund ($412,030.00). No additional budget appropriation is required.
Prior Council Review
None
Action Requested

On April 15, 2024, award a construction contract for the 2024 Joint Agency Slurry Seal Project to the lowest responsive and responsible bidder, Blackline, Inc, of Vancouver, Washington, at their bid price of $412,030.00, which includes Washington State sales tax, and authorize the City Manager, designee, to execute the same.

 

Chris Sneider, Senior Civil Engineer, 360-487-8239

 


ATTACHMENTS:
Description
2024 Slurry Seal Map
Contract